Skip to main contentSkip to navigation
Guide

Planning solar during a home renovation in Perth: timing, pre-wiring, and coordination

A home renovation is one of the best times to plan your solar and battery setup: walls are open, roof access is unobstructed, and conduit runs are cheap. Here's how to coordinate solar with your renovation in Perth.

By BillWise TeamFiled 19 June 2026Updated 14 Oct 20269 min read

A renovation is a good time to prepare your home for solar and battery storage, because walls are open and roof access is easier. Preparing during a renovation can cost significantly less than a standalone solar installation. The typical saving is approximately $620–$1,350.

Upload a recent Synergy bill to the BillWise bill analyser to see what your own usage may save.


Why is a renovation a good time to prepare for solar?

A renovation is a good time to prepare for solar because walls are open and roof access is easier. Running conduit inside an open wall costs $20–$80 for materials and about 30 minutes of electrician time. The same run in a finished home can add $300–$800 in labour. Switchboard work is often already budgeted.

A solar installation has two big cost parts: the equipment (panels and inverter) and the labour, especially conduit runs and switchboard work. During a renovation:

  • Conduit runs cost less when walls are open. Conduit is protective pipe for cables. A run from the roof to the switchboard, inside an open wall, costs $20–$80 for materials and 30 minutes of an electrician's time. In a finished home, the run needs cutting, patching, and repainting. That adds $300–$800 in labour.
  • Switchboard work is already budgeted. Most renovations require a switchboard upgrade. If you upgrade anyway, the extra cost of preparing for solar is minimal. That includes a main switch, space for a solar or battery circuit breaker, and earth bar sizing.
  • Roof access is easier. During reroofing or roof framing, it is easier to install roof penetrations (openings for cables or mounts), rafter brackets for flush-mount rails, or tiles set aside for conduit exits.

What should you do about solar if you are reroofing?

A reroof is the best opportunity to prepare for solar. Ask your solar installer to assess the roof framing before tiles go on. Before reroofing, install a 25mm conduit from the roof space to the switchboard, and leave it capped at the roof exit. Colorbond rail attachment uses clamps, with no penetrations.

Have your solar installer assess the roof framing before tiles go on. The solar installer can:

  • Identify the best rafter positions for rail attachment. These are typically 600mm centres, but this varies.
  • Advise on roof pitch and orientation for the highest output
  • Install roof penetrations (conduit exits, rafter brackets) while the roof is stripped

Request specific actions before reroofing:

  1. Install a 25mm conduit from the roof space to the switchboard location. You can pull the wires through later.
  2. Leave the conduit capped at the roof exit point
  3. Have the solar installer review the tile or metal interface for future rail attachment

For metal roofing (Colorbond): Rail attachment uses standing seam clamps or tri-clamp tiles, so there are no penetrations. This is easier than tiles.

For concrete or terracotta tile roofing: A roof penetration is standard. It is typically an aluminium flashing plate around a 40mm conduit. Install it before tiles go on.


What should your switchboard have for future solar?

Your switchboard should be prepared for solar even if you do not install panels yet. The minimum includes a dual-pole mains switch, at least 2 spare circuit breaker positions, and enough earth bar capacity. Ask your electrician to prepare the switchboard, because it adds minimal cost during a switchboard replacement.

Prepare the switchboard for future solar, even if you are not installing it right away:

Minimum pre-solar switchboard preparation:

  • Dual-pole mains switch (required for solar grid connection; a single-pole switch is not acceptable)
  • Spare circuit breaker positions (minimum 2): one for the solar inverter, and one for a battery or EPS circuit if a future battery is planned
  • Adequate earth bar capacity, because solar adds extra earth bonding requirements
  • Space for a bi-directional meter. If you are moving from a single-direction meter, your switchboard needs space for Western Power to upgrade the meter.

Ask your electrician directly: "Can you prepare this switchboard for future solar and battery installation?" It is a standard request. It adds minimal cost during a switchboard replacement.

Three-phase vs single-phase: If your renovation adds a large load, such as a large ducted AC, an EV charger, or a large workshop, consider three-phase power at this stage. Three-phase solar is available. It uses a three-phase inverter. Changing from single to three-phase supply later involves Western Power fees of $3,000–$8,000+. Doing it now can avoid that.


How do you coordinate a solar installer with your builder?

Solar installers are typically not managed by your builder, so you may need to coordinate them yourself. Involve the installer at the design stage, before the roof frame inspection, and before linings go on. Panels and the inverter are usually installed last. NCN with Western Power takes 5–20 business days.

Solar installers are a specialised trade. Your builder typically does not manage them as part of the standard construction programme. You need to coordinate them yourself.

Recommended sequence:

  1. During the design and approvals phase: Have a solar installer assess your renovation design. Check roof pitch, orientation, and shading from proposed new structures, such as a pergola, a second storey, or neighbouring buildings.

  2. Before the roof frame inspection: Have the solar installer attend, or give specifications to your builder or framing contractor. This covers rafter placement and roof penetration prep.

  3. Before internal linings go on: Have your electrician install conduit runs while walls are open. The solar installer should specify the conduit size, typically 25mm or 32mm, and the route.

  4. After switchboard installation, but before linings: Confirm the switchboard is ready for solar (see above).

  5. After practical completion, or as a last trade: The solar installer returns to install panels and the inverter, then commissions the system. NCN with Western Power takes 5–20 business days. Factor this into your handover timeline if you want the system running at move-in.


What should you do now, and what can wait?

Do the low-cost preparation during the renovation, while disruption is already happening. That includes conduit runs, switchboard preparation, roof penetrations or brackets if you reroof, and any three-phase upgrade. Panels, the inverter, and the battery can usually wait until after move-in. Pre-wiring for a battery is worth doing if you know where it goes.

Do now, during the renovation (low cost while disruption is already happening):

  • Conduit runs (roof to switchboard)
  • Switchboard preparation (main switch, spare positions, earth bar)
  • Roof penetrations or bracket installation if reroofing
  • Three-phase supply upgrade, if you plan large loads

Can wait until after move-in:

  • Panel installation
  • Inverter installation
  • Battery installation (but pre-wire for the battery location if you know where it goes)
  • NCN approval with Western Power

Pre-wiring for the battery is worth doing if you know where it will go. A 10kWh battery (Sungrow, BYD, or Alpha ESS) is typically wall-mounted in the garage or utility room. Pre-wiring a 240V circuit to that location, with conduit space for DC cables from future solar, can save $200–$500 later.


Do heritage rules limit where you can put solar in Perth?

Heritage overlays and built form rules may affect panel placement in some Perth suburbs. Panels visible from the street may need heritage council approval. Rear or side roof placement is typically accepted without full heritage approval. Trees removed during a renovation may be a good time to address shading.

Some Perth suburbs have heritage overlays or built form requirements, especially in inner suburbs and coastal areas. These can affect panel placement. Before your renovation design is final, check:

  • Heritage overlay: If your property is on the State Register or a local government heritage list, panels visible from the street may need heritage council approval. Rear or side roof placement is typically accepted without full heritage approval.
  • Tree clearing: If mature trees are removed during a renovation, it may be a good time to address future shading. Urban tree permits in Perth require landowner application. Trees on your own lot, with the landowner's approval, are generally permissible to manage.
  • Stormwater and drainage: Roof changes during a renovation may require updated stormwater plans. Solar panels affect how water runs off the roof.

How much can you save by preparing solar during a renovation?

The typical saving from preparing solar during a renovation is approximately $620–$1,350. That covers conduit runs, the switchboard main switch and spare positions, and roof penetration or bracket prep. The solar equipment itself costs the same either way. BillWise's calculator models solar, battery and tariff scenarios using Synergy tariffs. It does not replace an installer's site assessment.

Compare preparing during a renovation with retrofitting later:

Conduit run (roof to switchboard)
During renovation
$80–$200
Retrofit later
$300–$800
Saving
$220–$600
Switchboard main switch + spare positions
During renovation
$100–$300
Retrofit later
$400–$800
Saving
$300–$500
Roof penetration/bracket prep
During renovation
$100–$250
Retrofit later
$200–$500
Saving
$100–$250
Total typical saving
During renovation
Retrofit later
Saving
$620–$1,350
ItemDuring renovationRetrofit laterSaving
Conduit run (roof to switchboard)$80–$200$300–$800$220–$600
Switchboard main switch + spare positions$100–$300$400–$800$300–$500
Roof penetration/bracket prep$100–$250$200–$500$100–$250
Total typical saving$620–$1,350

The solar equipment itself, such as panels and the inverter, costs the same whether it is installed during or after the renovation. The saving comes only from electrical and building work, which is cheapest while the house is already open.


A renovation is often the cheapest time to prepare your home for solar, because the disruption is already happening. You may not be ready to buy panels and an inverter yet. Pre-installing conduit and switchboard preparation at renovation time can save $600–$1,350. It also avoids patching and repainting finished work later.

Upload a recent Synergy bill to the BillWise bill analyser to see what your own usage may save.

$Found this helpful? Share it!

Money-relevant figures in this article are checked against primary sources. Here’s how we check our facts.

Run your own numbers

Calculate your savings

See how much you could save with solar, batteries, and smart tariff choices

Related guides

Related articles

AC coupling vs DC coupling for solar batteries in Perth: what the difference means for you

Solar6 min read
Read →

Adding more solar panels to an existing system in Perth

Solar9 min read
Read →

All-black solar panels in Perth: aesthetics, cost, and performance difference

Solar6 min read
Read →

With your OK we use Google Analytics and Google Ads cookies, Vercel visit statistics, masked session recordings to find bugs, Microsoft Clarity recordings and heatmaps of how pages are used, and an anonymous copy of your calculator figures for local averages. None of it runs unless you accept.